Calling the Shot
date
newest »

message 1:
by
[deleted user]
(new)
Dec 16, 2010 08:40AM
Although the data is very dated, this brief discussion of programmer productivity is a reminder that in many areas of technology, we have not progressed much. I don't have recent data, but I wouldn't be surprised if the ~1500 LOC/PY figure is still the typical productivity for large projects. What has changed (described by the last two bullet points in the chapter) is the higher level of abstraction of what a "Line of Code" means.
reply
|
flag

I agree the lines/time metrics are likely to have greatly changed since this chapter was authored.
I liked the part that scoffs at using code/time as the estimator due to previous chapters mentioning that coding is half or less of the total effort.